Controllers

Clone Tools
  • last updated a few seconds ago
Constraints
Constraints: committers
 
Constraints: files
Constraints: dates
Bamboo Commit: Updated the Copyright section and replaced tabs with 4 spaces

  1. … 1 more file in changeset.
DEN-14561

Code review updates

  1. … 1 more file in changeset.
DEN-14604 updated the valves

DEN-14549: Fix art/ven pressure alarm check logic - apply user set limits in dialysis state (if not saline bolus) or treatment stop state (if BP running). Require door/latch to be closed in patient connection state. Remove escalation for prime complete alarms. Handle prime complete alarms in pre-tx recirculate state. Update prime complete alarm properties.

  1. … 5 more files in changeset.
DEN-14557 addressed a code review comment

DEN-14557 reversed the blood leak's pass/fail logic in the zero sequence

DEN-14557 added code to the HD valves to accept a transition command if the valve is currently is not close to target

DEN-14011: created handleDrySelfTestStartState. code review comments.

  1. … 1 more file in changeset.
DEN-14011: added condition to check if BP is running while we do occlusion checks.

Bamboo Commit: Updated the Copyright section and replaced tabs with 4 spaces

  1. … 8 more files in changeset.
DEN-14549: Rolled back change to include blood prime for normal inline pressure range checks. Leave as fixed max only range check in blood prime.

Merge branch 'staging' into DEN-14559-dg_hd_dev-hd_dg_dvt-update-part-8

DEN-14559 updated the code to be able to run POST requested by the Dialin user

  1. … 8 more files in changeset.
Fixed merge conflicts from staging.

DEN-14549: Added function to see if an alarm condition is detected. Added a function to determine whether A/C power loss condition is detected and used them where needed.

  1. … 5 more files in changeset.
DEN-14549: include venous check in including blood prime.

DEN-14549: Addressed code review comments.

  1. … 1 more file in changeset.
DEN-14549: clear treatment version of ac power loss alarm too when ac is restored. prevent pump current alarms when ac power loss in treatment is active too.

  1. … 1 more file in changeset.
HD-DEN-14561_Release Preprocessor Flag Specifies Code That Conflicts With SW Config Debug

Corrected _RELEASE_ logic, release build executes the same block as non debug selection

  1. … 2 more files in changeset.
DEN-14549: maintain blood flow rate when alarm w/ blood recirc property pauses treatment. maintain Heparin dispense when blood recirc is occurring during alarm pause of treatment. include blood prime state in checks for inline pressure range.

  1. … 3 more files in changeset.
DEN-14549: Misc updates to dry self-tests in pre-treatment.

  1. … 3 more files in changeset.
Bamboo Commit: Updated the Copyright section and replaced tabs with 4 spaces

DEN-14549: Removed some obsolete code.

  1. … 1 more file in changeset.
DEN-14310 Reset error counter if test inactive.

DEN-14549: Updates to reasons to reject start treatment request at standby mode.

  1. … 6 more files in changeset.
Bamboo Commit: Updated the Copyright section and replaced tabs with 4 spaces

  1. … 6 more files in changeset.
DEN-14549: Added buttons and safety line to HD events to be logged.

  1. … 1 more file in changeset.
Merge branch 'staging' into DEN-14497-dg_hd_dev-hd_dg_dvt-update-part-7

  1. … 6 more files in changeset.
DEN-14497 addressed the code review comments

  1. … 1 more file in changeset.
DEN-14310 Check for AC HD power lost for Valve position check.